First section of Redcar’s flood defence to be put in place
The first section of a new £30m sea flood defence is reportedly due to be lifted into place at Redcar.
It is part of a multi-million pound project to regenerate the town’s seafront.
The first section of wall will be made from pre-cast concrete sections which will be winched into place by a giant crane.
Approximately 1,000 pre-cast concrete units will make up the whole scheme. The first sections are being put into place around the old Leo’s Nightclub.
Over the last three months, 900 steel piles have been driven into the beach over a distance of 1,476ft (450m), to support the new sea wall.
The new defences at Redcar, which started in January this year, are expected to be complete in Spring 2013 and aims to reduce the risk of flooding to 1,000 properties in Redcar.
The new wall will stretch for 2.7 kilometres, from Coatham to the eastern end of the Stray, and is intended to reduce coastal erosion and flood risk for the next 100 years.
This was posted in Bdaily's Members' News section by Ruth Mitchell .
Enjoy the read? Get Bdaily delivered.
Sign up to receive our popular morning National email for free.
How businesses can reduce workplace safety risks with custom solutions
Tech firm unveils jobs plan after £530,000 backing
SMEs urged to think big at Newcastle event
B Corp is a commitment, not a one-time win
Government must get in gear on vehicle transition
A legacy in stone and spirit
Shaping the future: Your guide to planning reforms
The future direction of expert witness services
Getting people into gear for a workplace return
What to expect in the Spring Statement
Sunderland leading way in UK office supply market
Key construction developments in 2025