Sean Beach, Operations Manager Hartlepool, Chris Broughton, Business Development Manager and Roy Mer

PD Ports set to launch newly constructed £35m quay at Teesport

PD Ports is set to announce that its 550m deep water quay at Teesport is open for business following a £35m redevelopment.

The ports and logistics company now owns and operates some of the deepest general cargo berths in the UK. Number One Quay is being officially unveiled at Breakbulk Europe later this week.

The investment has created the capability to accommodate two fully laden 235m long panamax vessels simultaneously in water 14.5m deep. One major advantage of this is the ability to take bigger vessels – both for import and export – therefore driving down freight costs for customers.

The quay design also has the capacity to further deepen the berth pockets in the future as customer requirements dictate, and rail links to the quay edge and substantial warehousing on site have been maintained.

Number One Quay, which was originally constructed in the early 1960s, had reached its capacity in terms of the size of fully laden ships which could be handled as well as the demands of modern cranes and handling equipment.

The 18-month project involved the demolition of some 24,000 tonnes of the existing concrete quay deck with a similar amount of new concrete used in the reconstruction. Where possible, the original concrete was crushed and re-used in the new structure.

In addition, around 10,000m of 1.3m diameter heavy duty steel tubes were used for the supporting piles.

Dredging of the berth pockets was carried out by one of the largest backhoe dredgers in the world, the Manu Pekka, operated by Boskalis Westminster with up to 260,000m3 of material being removed for disposal at sea.

Another advantage of the new quay is it opens up opportunities in new sectors, enabling the mobilisation and demobilisation of a lot more deep sea bulk cargoes from all over the world.

As well as the increased depth, the new quay deck is designed with a much higher loading capacity to take the loads from modern handling equipment including the existing Mobile Harbour Cranes.

Whereas before it could only take 2.5 tonnes per sq m, now it can take 10 tonnes per sq m making the quay suitable for the mobilisation of wind farm installation vessels.

Mark Pearson, PD Ports’ project director, said: “The reconstruction of Number One Quay gives us a tremendous platform to grow our business while increasing its lifespan for another 70 to 80 years.

“We are pleased to have secured funding through the Regional Growth Fund to help deliver this project for which our application was supported by Tees Valley Unlimited.

“These works are an important addition to our wider growth plans at Teesport and its pivotal role in driving government plans to rebalance trade through the Northern Powerhouse movement. Ultimately this will provide more direct and efficient routes to market for Northern importers and exporters.

“Ships are getting bigger and carrying more cargo so our improved facilities give customers a freight advantage. We are ensuring that Teesport has the right infrastructure and equipment to encourage and support future growth for PD Ports and our customers.”

Looking to promote your product/service to SME businesses in your region? Find out how Bdaily can help →

Enjoy the read? Get Bdaily delivered.

Sign up to receive our daily bulletin, sent to your inbox, for free.

* Occasional offers & updates from selected Bdaily partners

Our Partners