Hi-tech horticultural specialist CambridgeHOK have completed the build of an “impressive” £5m food packhouse in which millions of cucumbers and tomatoes will be automatically weighed, sorted, quality checked and stored ready for delivery to supermarkets.
The project, for Fenland Glasshouse Limited, a company owned by funds managed by Schroders Greencoat LLP, was completed on time in just under a year. East Yorkshire based CambridgeHOK were approached early last year to discuss, plan and design the project with groundworks and civils beginning on the site in Ely, Cambridgeshire, in July 2022.
The 3,500 sq metre facility has now been handed over to the client after some final additional requests were completed, with the site now fully operational and handling more than a million cucumbers and 600,000 packets of tomatoes a week.
The process within the packhouse is almost entirely automated once cucumbers and tomatoes have been picked from the adjacent glasshouse, which is one of the largest ever constructed in the UK with a footprint of over 22 hectares.
They are collected and graded into sizes, quality checked, wrapped and boxed, ready to be collected and delivered to several large UK supermarkets the next day.
Project manager Elliot Wrightson commented: “This has been an exceptional project to be involved in and we were thrilled to be chosen to design and build this facility at CambridgeHOK, especially given the advanced technologies and levels of automation involved within the packhouse.
“The processes inside meant that the packhouse had to be built to a size which ensured it had the capacity required, given the huge level of daily fruit production in the glasshouse, and it also had to be designed and built in a Venlo style, as it connects directly to the glasshouse.
“Considerations also had to be made in the design for the high levels of automation within the packhouse, and for there to be zoned areas with differing temperatures in the packing hall, the tomato zone and the cucumber zone.”
CambridgeHOK completed works including preparing more than 100 tonnes of steelwork at its factory in Newport, East Yorkshire, including trellis beams up to 16m long. On site it completed foundations and civils, the build, external cladding, cold store panelling and the mechanical and electrical systems.
The 30-strong CambridgeHOK site team used 40mm cladding on the exterior of the building and 100mm cold store panelling on the interior and ceilings. HVAC, electrical and lighting systems and climate controls were also installed, as were internal partitions and access and loading doors, with support also provided to coordinate the final internal fit-out.
By Matthew Neville – Senior Correspondent, Bdaily
- Add me on LinkedIn and Twitter to keep up to date
- And follow Bdaily on Facebook, Twitter and LinkedIn
- Submit press releases to editor@bdaily.co.uk for consideration.
Looking to promote your product/service to SME businesses in your region? Find out how Bdaily can help →
Enjoy the read? Get Bdaily delivered.
Sign up to receive our popular Yorkshire & The Humber morning email for free.