Somerset manufacturer delivers £2m contract for Canary Wharf Group
Highbridge-based Offsite Solutions, the UK’s leading bathroom pod specialist, has delivered a £2m contract to manufacture 356 GRP shower pods for Canary Wharf Group. This is also the first application of its new GRP tile-effect finishes.
The pods are for two residential buildings under construction in the heart of London’s Docklands. The development will provide 297 fully serviced apartments and has been designed by HTA Design to reflect the area’s naval heritage.
Offsite Solutions produced the shower pods for Wood Wharf in two different sizes and configurations, and each was fully finished and fitted out offsite at its Highbridge factory before delivery to site.
The design options for Offsite Solutions’ highly successful range of GRP pods have recently been expanded to offer five tile-effect finishes specifically developed for the build-to-rent sector. This latest innovation in pod technology widens the scope of factory-finished GRP shower rooms and bathrooms.
The pods for Wood Wharf are the first to use Offsite Solutions’ new mosaic tile-effect finish and the first to feature a second GRP finish in each pod. The walls to the non-wet areas have an integral square tile-effect to contrast with the mosaic finish used above the hand basin and in the shower.
James Stephens, managing director of Offsite Solutions, said, “The capital costs of GRP pods can be up to 20 per cent less than steel-framed pod solutions, helping developers and BTR operators to meet their budget aspirations as well as reduce operating costs because there is no grout or tiling to the wet areas.”
“Our new range of tile-effect finishes now takes the aesthetic appearance of GRP pods to another level and allows more design flexibility. Our expanded range of GRP options has been very well received by developers, contractors and architects and it is great to see the first project now delivered.”
Colin Holder, senior project manager at Canary Wharf Group, said, “We were very happy with the standard of the pods and Offsite Solutions’ performance on this contract. The tile effect is exactly what the design team was looking to achieve.”
“Bathroom pods give us the benefits of speed and cost efficiency. These factors and the site constraints were the main drivers to manufacture the bathrooms for this scheme offsite. We estimate pods reduced work on site by up to three weeks per bathroom – as we could progress work on site while the bathrooms were fully finished offsite in the factory. This programme saving was significant.”
By Mark Adair – Correspondent, Bdaily
- Add me on LinkedIn and Twitter to keep up to date
- And follow Bdaily on Facebook, Twitter and LinkedIn
- Submit press releases to editor@bdaily.co.uk for consideration.
Looking to promote your product/service to SME businesses in your region? Find out how Bdaily can help →
Enjoy the read? Get Bdaily delivered.
Sign up to receive our popular morning London email for free.